2014-02-28 11:07:31 CET

2014-02-28 11:08:22 CET


REGULATED INFORMATION

English
Talvivaaran Kaivososakeyhtiö Oyj - Interim Management statement

Talvivaara Mining Company Interim Management Statement for the fourth quarter and year ended 31 December 2013


Stock Exchange Release
Talvivaara Mining Company Plc
28 February 2014


 Talvivaara Mining Company Interim Management Statement for the fourth quarter
                        and year ended 31 December 2013

          Talvivaara's corporate reorganisation proceedings commenced



Highlights of Q4 2013
  * Nickel production of 1,559t and zinc production of 4,179t
  * Production impacted by a four week stoppage at the metals recovery plant in
    November-December,  due to dilute leach solutions which rendered production
    uneconomical
  * Bioheapleaching of the new ore heaps progressed in line with best ever heaps
    historically, enabling significant improvement in solution grades following
    the metals plan stoppage
  * Mining and materials handling (crushing, stacking, reclaiming) operations
    suspended in November for the time being due to the Company's tight
    financial situation
  * Talvivaara Mining Company Plc and its operating subsidiary Talvivaara
    Sotkamo Ltd applied for corporate reorganisation on 15 November 2013, and
    the reorganisation proceedings of the two companies commenced on 29 November
    2013 and 17 December 2013, respectively


Highlights of 2013
  * Nickel production of 8,662t and zinc production of 17,251t
  * Water balance challenges impacted production throughout the year as a
    consequence of flooding of the existing ore heaps and inactivation of the
    bioheapleaching process in them
  * Ore production temporarily suspended from September 2012 to mid-May 2013;
    after re-start, record levels of output in mining and materials handling
    were achieved
  * New heaps stacked since the re-start of mining in May performed well and
    started contributing to metals production in Q4 2013
  * EUR 261 million rights-issue completed in April 2013; cash-burn thereafter
    higher than anticipated due to the prolonged impact of water on production
    and weak nickel prices


Highlights of Q1 2014 to date
  * Year-to-date nickel production of 2,047t and zinc production of 3,638t until
    27 February 2014
  * Current month nickel production through 27 February 1,225t of nickel and
    1,991t of zinc;
    current February will be the best production month since August 2012
  * Metals plant operating uneventfully with daily nickel production amounting
    to 45-55t and nickel grade in leach solution currently at around 1.5-1.6g/l
  * Ore production remains suspended until further financing is secured


Guidance for 2014
Talvivaara's operational outlook in 2014 is dependent on the success to
completion, timing and extent of the short term financing transactions currently
being negotiated. In the absence of a committed financing solution and related
operational plan for the time being, Talvivaara is not yet in a position to give
guidance on its production or its operational and capital expenditure for the
current year.


CEO Pekka Perä comments: "The past year was a very challenging period for us due
to  the prolonged inhibiting effect of water  on our bioleaching process and the
persistently  low nickel price since last  spring. As these two factors severely
impacted  our cash-flows, and  as substantial efforts  and spending also went to
managing our water balance and its environmental impact, our financial situation
deteriorated  such that we were forced  to apply for corporate reorganization in
November.  The reorganization proceedings  are now on-going  both for Talvivaara
Mining  Company Plc and its operating subsidiary, Talvivaara Sotkamo Ltd, and we
are  working, together with  the court appointed  administrator, towards finding
the  short as  well as  the long  term financing  solutions for  the Group going
forward.

Whilst  our nickel production only amounted to 8,662 tonnes in 2013 and we ended
the  year having had to suspend our  mining and materials handling functions for
the  time  being,  there  are  also  some  clear  positives  to  be  noted. Most
importantly,  our new ore heaps, primary heaps 1 and 4, are performing very well
and  started contributing  to our  metals production  in the fourth quarter. The
nickel  grade in solution pumped to the  now steadily operating metals plant has
risen   from   less   than  1g/l in  November  to  around  1.5-1.6g/l currently,
demonstrating  that the technology works well when the heaps are constructed and
managed  properly - a lesson we have  learned after having struggled with poorly
functioning  heaps and  excess water  over the  last two  years. Along  with the
improved  metal grades, a clear proof of active leaching is also the temperature
of  the solution coming out  of the heaps: last  winter the solution temperature
went  down to  6C, while this  year the  lowest temperatures have remained above
20*C.

It  also deserves to  be noted that  before suspending the  mining and materials
handling  operations in  November, we  broke all  monthly production  records in
these two functions and were able produce ore at annualized capacities of around
18 million tonnes, corresponding to more than 40,000 tonnes of nickel contained,
for several months in a row.

Excess  water and risks related to it was  one of our key focus areas throughout
2013, and  although  long  term  solutions  to  the  water balance will continue
requiring  more work, we did  manage to reduce the  risk level through increased
recycling  of process  waters and  treatment and  discharge of  some 5.7 million
cubic  meters of water from the mine area. A recent test to our water management
capabilities  was the unusually mild month of December, during which practically
all  snow melted,  and approximately  one fourth  of the typical annual rainfall
fell in the area. Since December, the situation has stabilized and we anticipate
being  able  to  manage  the  forthcoming  spring  melt  with our existing water
management  systems. However,  we are  implementing further  improvements to our
reverse osmosis water treatment capacity and storage volumes in order to reach a
sustainable water balance in all conditions in the future.

For  our long  term future,  our most  important target  in the  near term is to
secure  sufficient  funds  to  allow  us  to re-start our re-claiming and mining
operations.  Having  these  two  functions  operational  helps  us  in our water
management  efforts and  creates the  foundation on  which we can again continue
ramping  up our production in anticipation of volume based cost benefits as well
as improving nickel prices.

Now  that our corporate reorganization  proceedings and re-financing efforts are
ongoing,  we have had to lay  off part of our personnel  for the time being, and
all  our employees have had to endure  uncertainty over the future of their jobs
and  Talvivaara's  operations.  Whilst  I  strongly  believe  in  the  long term
viability  of  the  Talvivaara  mine,  I  am  also  sincerely  grateful  for our
personnel's  commitment  through  these  challenging  times  and look forward to
seeing their efforts carry the operation into a stable and profitable future."


Enquiries:

Talvivaara Mining Company Plc Tel. +358 20 712 9800
Pekka Perä, CEO
Saila Miettinen-Lähde, Deputy CEO and CFO

INSTINCTIF Partners Tel. +44 207 457 2020
David Simonson
Anca Spiridon


Conference call 28 February 2014 at 12.00 noon GMT / 2.00 pm EET

Participant - Finland: +358 (0)9 2313 9201
Participant - UK: +44 (0)20 7162 0077
Participant - US: +1 334 323 6201

Conference id: 942119



Nickel market remained weak for most of 2013

In  2013, the  nickel  market  was  impacted  by  oversupply and relatively weak
demand.  Having traded at around USD 17,000-18,000/t for the first two months of
the  year, the  nickel price  declined down  to below  USD 14,000/t in  June and
stayed  around the same  level for the  remainder of the  year, averaging at USD
14,000/ for the second half of the year.

Whilst nickel demand in China continued to play a significant part in the nickel
market  and  nickel  price  development  throughout  the  year,  a  particularly
important role was played by production of the Indonesian nickel containing iron
ore  which is used to make a ferronickel product called Nickel Pig Iron ("NPI").
The NPI production has grown steadily over the recent years and was estimated at
some  460,000 tonnes  in  2013, measured  by  nickel  content,  which represents
approximately  24 per cent of the global nickel  supply. The majority of the NPI
is  used for the production  of stainless steel in  China, and over the last few
years,  the marginal cost of nickel production from NPI has fallen substantially
as  a result of technical development. This has made NPI a cost-efficient source
of nickel for China and in part contributed to the weak nickel price development
during  the past  year. However,  on 12 January  2014, the Indonesian government
implemented  a ban on unprocessed NPI ore  exports, which may have a substantial
impact  on nickel  supply, the  average marginal  cost of nickel production, and
nickel  price  in  the  future.  Whilst  the  impact  is  not  anticipated to be
immediate,  e.g. due to reportedly large NPI stocks in China, the market outlook
towards  the end of 2014 and beyond is  cautiously more optimistic than still at
the end of 2013.

Global  primary  nickel  consumption  grew  slightly  during  2013, and  Chinese
consumption  was at approximately  850,000 tonnes representing approximately 45
per  cent of the global market. On the supply side, global primary nickel supply
amounted  to  1.9 million  tonnes  in  2013, leaving  the market at a surplus of
approximately 100,000 tonnes. (Source: Reuters,INSG)

The EUR/USD exchange rate showed an increasing trend towards the end of the year
having  traded at around 1.30 during the spring  and moving up to around 1.37 by
the  end of the year. Whilst the strengthening of the Euro reflected in part the
subsiding  of the  Eurozone crisis,  it exacerbated  the impact  of the  weak US
dollar nickel price on Euro cost based producers such as Talvivaara.

Review of operations

Q4 2013
Nickel   and   zinc  production  in  Q4  2013 amounted  to  1,559t and  4,179t,
respectively.  Production was limited due to  the low leach performance from the
two  old heaps (primary heaps 2 and 3) while  two new heaps (primary heaps 1 and
4) were  being brought  into operation,  but not  yet at their peak performance.
Heap  4 started  positively  contributing  to  nickel  production  at the end of
October  and heap 1 reached positive contribution  at the beginning of December.
Both heaps showed good ramp up, with performance in line with best ever leaching
results.

The  production output was also impacted by an approximately four-week shut down
of  the metals plant in November-December. The stoppage was taken to address the
nickel  grade in  the leach  solution, which  had depleted  to levels which made
operation  of the metals recovery plant  uneconomical. The shut-down allowed the
leach solution grade to increase as the two new heaps increased in grade, and by
the  time  the  plant  restarted,  nickel  grade  in solution had increased from
0.7g/l to  1.3g/l. The nickel grade  in solution pumped  to the metals plant has
since continued to rise despite high production rates from the new heaps.

Significant   effort  was  made  during  the  period  to  improve  the  leaching
performance  of heaps 2 and 3. These heaps have struggled to operate since 2012
when  heavy  rains  resulted  in  the  heaps  flooding  and  the  leach reaction
practically stopping. Acid addition to the heaps was increased to help modify pH
and return the heaps to better leach conditions. Modifications to the surface of
the  heaps  were  also  made  and  aeration  pipes re-opened to improve solution
percolation  and aeration.  Some of  these actions  showed promising  short term
gains  but the improvements were not  sufficient to justify continued additional
costs of the actions taken.

Due to the financial situation of the Company, all mining and materials handling
operations were suspended from 13 November 2013. Prior to the suspension, mining
and  materials handling operated well during the quarter, with new records being
achieved  for mined  tonnes, and  tonnes crushed.  Just prior to the suspension,
significant  improvements  had  also  been  made  in  reclaiming  allowing major
bottlenecks in the process to be identified and removed.

Q1 2014 up to 27 February
As  a result of the improved grades in leach solution from the new primary heaps
1 and  4, the nickel grade in  solution pumped to the  metals plant has risen to
around  1.5-1.6g/l currently. The metals plant  has operated steadily during the
early part of 2014 and is currently producing 45-55t of nickel on a daily basis.
The  year-to-date  production  through  27 February  2014 has totalled 2,047t of
nickel  and  3,638t of  zinc.  The  current month production through 27 February
2014 has  amounted to 1,225t of nickel and  1,991t of zinc, making this February
the best production month since August 2012.

The cost efficiency of production at the metals plant has significantly improved
as  a result of the higher metal grades in solution as well as the substantially
higher  temperature of  the leach  solution compared  to the winter of 2013. The
increased solution temperature, around 20°C this winter vs. 6°C the year before,
reflects  the high level of chemical and  biological activity in the new primary
heaps 1 and 4.

Mining and materials handling remain suspended for the time being, with re-start
planned for Q2 2014 but subject to securing sufficient further financing.

Full year 2013
Talvivaara  closed the year having produced 8,662t of nickel (2012: 12,916t) and
17,251t of   zinc   (2012:   25,867t). Over  the  course  of  2013, Talvivaara's
operations  continued to be  impacted by water  balance issues stemming from the
heavy  rains of 2012 and the gypsum pond leaks of November 2012 and April 2013;
hence  one of the key areas of activity  was to establish measures to purify and
release  excess waters captured at the mine area. Ore production re-commenced in
mid-May 2013 after having been suspended from September 2012 due to excess water
in the open pit. After successful operation from May to November, ore production
was  again  suspended,  this  time  for  financial  reasons. Metal grades in the
bioleaching  solutions suffered from  the prolonged effects  of water on the old
heaps and decreased through most of the year until the newly stacked ore started
to  contribute  to  production  in  the  fourth  quarter.  Metals recovery plant
operation  and  availability  improved  steadily  through  the  year without any
extended stoppages relating to unexpected equipment failures.

Mining  and materials handling produced  7.4Mt and processed 7.6Mt of ore (2012:
8.7Mt), and  mined 3.1Mt of  waste (2012:  5.3Mt) in 2013 during  the six months
from  May to November that these functions were operational. A record production
level  of  1.66Mt per  month  was  achieved  in October before the operation was
suspended.  The amount of nickel  in the ore stacked  to leaching in October was
4,064t. The step change seen in the productivity, quality and capacity of mining
and  materials handling was  achieved through stricter  grade control, increased
cut-off  grade, enhancement  of the  agglomerate quality  control, focus on unit
costs, and de-bottlenecking of the reclaiming operation.

In  bioheapleaching the  average nickel  grade through  the year  was 0.97g/l.
Special  attention  was  paid  to  various  operational  measures to enhance the
performance  of the existing heaps and to ensure outstanding start-up of the new
heaps.  Significant improvement compared to the  previous year was achieved with
the  new heaps, whereas the actions to improve the operation of the old heaps 2
and  3 proved not to  be cost efficient  enough. The well  performing new heaps,
which  cover  approximately  40 per  cent  of  the  total primary leaching area,
together  with the secondary  leaching, enabled the  realized increase in metals
production at the year end and going into 2014.

In  metals  recovery,  plant  stability  and  availability continued to improved
compared  to previous years. De-bottlenecking actions were successfully executed
allowing  leach solution flow rate to increase up to 1,750m3/h. The average feed
flow  rate for the entire year  was 1,142 m3/h.  Unexpected process or equipment
related  downtime was  approximately one  week through  the entire year, proving
maturity of the processing technology.

The  challenging water  balance situation  continued throughout  the year 2013.
Additional  storage and purification capacity  was built for stored contaminated
waters  and  reverse  osmosis  units  were  commissioned  mid-2013 for purifying
circulated water for metals recovery plant usage.



Production key figures

------------------------------------------------------
                                Q4    Q4     FY     FY
                              2013  2012   2013   2012
------------------------------------------------------
 Mining
------------------------------------------------------
 Ore production       Mt       1.6     -    7.4    8.7
------------------------------------------------------
 Waste production     Mt       0.9   1.2    3.1    5.3
------------------------------------------------------
 Materials handling
------------------------------------------------------
 Stacked ore          Mt       1.7     -    7.6    8.7
------------------------------------------------------
 Bioheapleaching
------------------------------------------------------
 Ore under leaching   Mt      51.8  44.3   51.8   44.3
------------------------------------------------------
 Metals recovery
------------------------------------------------------
 Nickel metal content Tonnes 1,559 2,317  8,662 12,916
------------------------------------------------------
 Zinc metal content   Tonnes 4,179 4,106 17,251 25,867
------------------------------------------------------


Financial status and going concern

On  10 October 2013, the Company  announced that, as  the market price of nickel
had  declined by more  than 20 per cent  since the first  quarter of 2013 and as
Talvivaara's production had continued to be impacted by the prolonged effects of
excess  water on older  ore heaps, Talvivaara's  liquidity position had weakened
more  than anticipated. In addition, on 7 November 2013, Talvivaara announced in
its  interim report for the  nine months ended 30 September  2013 that it was in
advanced  discussions with certain stakeholders  concerning a financing solution
that  would address Talvivaara's current  liquidity needs. On 15 November 2013,
the Company announced that it had become evident as a result of such discussions
that  additional liquidity would  not be available  for Talvivaara as  part of a
voluntary  restructuring. Therefore,  the Company  and its  operating subsidiary
Talvivaara Sotkamo applied for a corporate reorganisation on 15 November 2013 by
filing  related  applications  with  the  district  court of Espoo, Finland. The
district court of Espoo took the decision to commence a corporate reorganisation
process  in  respect  of  the  Company  on  29 November  2013 and  in respect of
Talvivaara Sotkamo on 17 December 2013.

As  at 31 December 2013, Talvivaara  had cash and  cash equivalents amounting to
EUR  5.9 million. As  a result  of cash  generated from  nickel and cobalt sales
since then, and the cost savings made by restricting operations, the Company has
been  able to continue operations for the time being. However, in the absence of
further  funding, the Company's liquidity situation remains critical. Talvivaara
is,  together with the Administrator, in  active discussion with certain parties
regarding  bridge funding and will inform the  markets about the progress in due
course.  In addition,  the Company  is also  in discussions with certain parties
regarding a long-term financing solution for Talvivaara

As  also stated in connection with  the Company's Q3 2013 results, the directors
have  in  the  current  circumstances  concluded  that  there  exists a material
uncertainty  that  casts  significant  doubt  upon  the  Company  and Talvivaara
Sotkamo's  ability to continue as a going concern and that, therefore, the Group
may  be unable to realise its assets and discharge its liabilities in the normal
course of business.

Anticipated impairment charges in FY 2013 accounts

Deferred tax assets
Talvivaara  has continued to  recognise deferred tax  assets on its consolidated
balance  sheet through Q3 2013 and the  amount of deferred tax assets recognized
on  tax loss carryforwards as at 30 September 2013 amounted to EUR 136.5 million
(31  December  2012: EUR  103.8 million).  In  its  Q3 2013 interim results, the
Company announced having reviewed the past operational challenges which have led
to  lower than  expected production  and profitability  levels at the Talvivaara
mine.  It was further noted that  if Talvivaara generates future taxable profits
lower  than those assumed  by the management  in determining the  amounts of the
recognized  deferred tax assets, the assets  may become impaired, either in part
or  in full. Accordingly, the  amounts recognized on the  balance sheet could be
reversed through profit and loss.

Having  now undertaken a review of the  amount of deferred tax assets recognized
on  tax loss carryforwards, the management has,  due to the historical losses of
the  mine project, the experienced delays in the ramp-up process and the current
financial situation of the Company, concluded that it will de-recognize deferred
tax assets in the amount of EUR 80.5 million in its FY 2013 results, leaving the
Company with a zero net deferred tax position.

Despite  the de-recognition  of the  deferred tax  assets, subject to Talvivaara
obtaining  sufficient financing to  continue the ramp-up  of its operations, the
Group  may  be  able  generate  sufficient  taxable  profits  so that all of the
deferred tax assets could be utilized in the future.

Potential impairment of inventory and property, plant and equipment
Talvivaara  is currently  reviewing the  valuation of  its inventories,  and its
property,  plant and equipment.  The management sees  is likely that substantial
impairments to these will be made in the Company's FY 2013 results.

Progress of corporate reorganisation

Upon  deciding to  commence the  reorganisation proceedings  of the  Company and
Talvivaara  Sotkamo on 29 November  2013 and 17 December 2013, respectively, the
district  court  of  Espoo  appointed  Mr. Pekka Jaatinen, Attorney-at-Law, from
Castrèn  &  Snellman  Attorneys  Ltd.  to  act  as  the  Administrator  for both
processes.

On  17 January 2014, the  District Court  of Espoo,  Finland, issued a ruling in
respect  of certain  deadlines in  connection with  the Company's and Talvivaara
Sotkamo's respective corporate reorganisations. According to the Court's ruling,
reports  on the financial status  of both companies have  to be completed by 28
March  2014, and  proposals  for  their  respective reorganisation plans must be
submitted  by the Administrator by  28 May 2014. Furthermore, the District Court
of  Espoo, Finland,  has appointed  creditor committees  in connection  with the
corporate  reorganisations of the Company and Talvivaara Sotkamo, which will act
as the joint representatives of the creditors in the reorganisation proceedings.
Various  creditor groups, including secured creditors, other debt financiers, as
well  as business  partners and  subcontractors essential  for the operations of
both  companies, will be represented in the creditor committees appointed by the
Court.  The creditor committees of the Company and Talvivaara Sotkamo shall each
have the same composition.Financing and commercial arrangements

Uranium off-take agreement with Cameco
In February 2013 Talvivaara entered into an amendment agreement with Cameco.
Under the agreement the amount of the up-front investment that Cameco is to pay
to Talvivaara for the construction of the uranium extraction facility was
increased by USD 10 million to USD 70 million, and the duration of the amendment
agreement extended to 31 December 2017 and commercial terms revised accordingly.
Cameco paid the additional up-front payment in February 2013.

Zinc streaming agreement with Nyrstar
On 14 February 2013, Talvivaara Sotkamo entered into an amendment agreement with
Nyrstar  regarding the zinc in concentrate streaming agreement pursuant to which
Nyrstar  made an  additional up-front  payment of  EUR 12 million  to Talvivaara
Sotkamo  in return for Talvivaara Sotkamo agreeing not to charge Nyrstar the EUR
350 per tonne extraction and processing fee on the next 38,000 tonnes of zinc in
concentrate  delivered  to  Nyrstar  as  was  agreed  in  the  original  zinc in
concentrate  streaming agreement. The up-front  payment was received in February
2013.

Share issue pursuant to the shareholders' pre-emptive subscription right
On 8 March 2013, an Extraordinary General Meeting of Talvivaara Mining Company
resolved to approve the proposal by the Board of Directors to authorise the
Board of Directors to undertake a share issue for consideration pursuant to the
shareholders' pre-emptive subscription right. The share issue was finalised in
April and all 1,633,857,840 new shares offered in the rights issue were
subscribed for. The gross proceeds amounted to approximately EUR 261 million and
the total number of shares in Talvivaara Mining Company increased to
1,906,167,480 shares.



Geology

In  early  2013 Talvivaara  undertook  a  project  to  update  its  ore reserves
estimates  and anticipated announcing the new reserves during the second half of
2013. However, due to the Company's prioritization of the use of human resources
and  funds  during  the  course  of  2013 and currently, the finalization of the
reserves  has been postponed for the time being. Talvivaara notes, however, that
the mineral resources in Talvivaara remain at above 2 billion tonnes of ore, and
that the short to medium term mine plan is not impacted by the delay in updating
the ore reserves.

Sustainable development, safety and permitting

Sustainable development and the environment
Water management continued to be in focus at Talvivaara also in 2013. A specific
water  management  organization  was  established  for  the  purpose  and also a
temporary  assignment, Project  Otter, was  established to  deal with  the acute
water balance situation. One of the key targets of Project Otter was to separate
rain  and  run-off  waters  from  contaminated  waters to minimize the amount of
waters having to be treated prior to discharge. In 2013 the Company succeeded in
substantially  reducing the  catchment area  by new  dams, trenching and pumping
stations.  Through the reduction of the catchment  area, e.g. the amount of run-
off  waters that accumulated  in the Kortelampi  dam during the  spring melt was
also significantly decreased. In total, some 5.7 million cubic meters of treated
waters were discharged from the mine area in 2013.

Subsequent  to the earlier leak in  Talvivaara's gypsum pond in November 2012, a
new  leak in it  occurred on 7 April  2013. In total approximately 400,000 cubic
meters  of water was leaked.  The leak was blocked  within 24 hours of its start
and no leakage waters escaped outside the mining area, as all of the waters were
caught  in emergency ponds and dams. The location of the leak was in an adjacent
section  to the section that leaked in  November 2012. The risk level related to
the  water stored in the gypsum pond has since the leak been lowered by reducing
the  amount of water  in the pond.  Currently, there is  still approximately one
million  cubic  meters  of  excess  water  in  gypsum  pond  section  5 and  6.
Neutralisation  of  this  water  commenced  during  the  autumn  of 2013, and in
compliance  with the request by the  relevant authorities, the excess water will
be removed from the gypsum pond by the early autumn of 2014.

During   the   summer   and   autumn  of  2013, the  emergency  volumes  of  the
bioheapleaching   circulation  were  substantially  increased  as  a  result  of
effective  evaporation  from  the  heaps.  The  emergency  volumes  in  the heap
circulation  decreased again towards the end of 2013 due to the unseasonal rains
and  melting of  snow in  December, which  resulted in approximately 1.2 million
cubic  meters of additional water in the  mining area. In order to alleviate the
situation  and to secure sufficient emergency  volumes, Talvivaara had to remove
water  from the heap circulation and store  a total of some 141,000 cubic meters
of  raffinate, the  metals plant  return solution,  in the  open pit which still
contains  also  waters  stored  there  in  2012. The  emergency volumes in leach
circulation reduced again due to freezing of the irrigation system in the poorly
functioning  primary  heaps  2 and  3 in  January 2014, resulting in the Company
having to pump another approximately 167,000 cubic meters of raffinate partly to
the  open pit  and partly  to the  empty solution  ponds of the uranium recovery
plant.  In addition  to the  raffinate, some  176,000 cubic meters  of solution,
which contained dilute secondary heap leach solution and run-off waters from the
waste  rock area, was pumped into the open pit, as the raffinate discharge alone
did not remove enough water from the heap circulation. Talvivaara will treat the
waters  stored in the open pit along with other excess waters in accordance with
the requirements set in its environmental permit.

Talvivaara  reached a  significant milestone  in its  water management,  when in
October  2013 a  closed  circuit  of  process  waters  at  the  metals plant was
achieved.  As  a  result  of  the  closed  circuit,  the  plant  can  in  normal
circumstances  be operated without additional raw water intake and use the water
produced by the reverse osmosis units.

As  a  result  of  investments  made  already  in  the previous years, the odour
discharges  relating to  hydrogen sulphide  and dust  emissions from  the mining
operations  have been clearly within the permitted limits. This has been evident
also  from the reduced  number of related  notices by the  neighbours. In 2013,
odour inducing concentrations decreased further by approximately 30 per cent and
the  odour related notices made by  the neighbouring residents reduced by 60 per
cent.

In 2013 the International Nickel Institute conducted an international life cycle
analysis  of  nickel,  covering  almost  all  western  world  nickel  producers.
According to the study, Talvivaara's climate and environmental impact as well as
energy  consumption per ton of nickel produced  are clearly below the average of
the  nickel industry. Due to  the energy efficient process  used by the Company,
Talvivaara's  greenhouse gas emissions are 39 per  cent and the usage of primary
energy 21 per cent lower than those of the average nickel producer. Talvivaara's
sulphur  dioxide emissions  are only  2 per cent  of the  average of  all nickel
producers.

Talvivaara   has   since  2010 had  a  certified  ISO  14001 standard  compliant
environmental   management  system.  The  Company  is  also  preparing  for  the
implementation  of ISO 9001 standard compliant quality and OHSAS 18001 compliant
occupational  health  and  safety  management  systems.  Certification  of these
systems is anticipated to be sought in 2015.

Safety
With  respect to safety issues  Talvivaara's goal is a  safe and healthy working
environment.  The Company  is committed  to continuously  improving its process,
product  and occupational safety. In  2013 Talvivaara focused on the improvement
of the entire organisation's safety culture.

In  the autumn of  2013, an independent safety  consultant, DuPont, conducted an
initial  evaluation of Talvivaara's safety  culture. Talvivaara will develop its
operations  in the future based on the improvement proposals made by DuPont, and
the  evaluation along  with the  improvement plans  will help  Talvivaara in its
pursuit towards its zero accident target.

The  injury frequency in 2013 was  30.4 lost time injuries/million working hours
(2012: 16.6 lost time injuries/million working hours).

Permitting
At the end of May 2013, Talvivaara received from the Northern Finland Regional
State Administrative Agency ("AVI") an environmental permit decision relating to
the storage, treatment and discharge of waters to the Oulujoki and Vuoksi water
systems. The permit decision contains regulations pertaining to, amongst others,
treatment and storage of waters and permit limits for discharges into downstream
water ways. The permit decision removes the annual 1.3 million cubic meters
discharge quota for purified waste waters, which has in part caused the
accumulation of excess waters at the mine site. The permit conditions pertaining
to maximum concentrations of harmful substances, among others sulphate, and
maximum discharge flow rate will however restrict the volume of discharged
waters in the future.

The  permit decision required the  Company to direct the  water contained in the
existing gypsum ponds to neutralisation or back to leach solution circulation by
31 October  2013. The  Vaasa  Administrative  Court  subsequently  extended  the
deadline until the end of 2013. After this, the Company applied for and obtained
permission  from the AVI for a two-staged emptying schedule such that section 5
of  the gypsum pond should be void of  excess water by the end of January 2014,
and section 6 by the end of August 2014. Prior to the end of January, Talvivaara
notified   the  Kainuu  Centre  for  Economic  Development,  Transport  and  the
Environment  ("Kainuu ELY-Centre") of  its inability to  comply with the interim
deadline  of  January,  however  stating  that  the  Company  believes the final
emptying  deadline for the entire pond to  be achievable. After this, the Kainuu
ELY-Centre  has requested section 5 of  the gypsum pond to  be emptied of excess
water  and the Kortelampi dam to be arranged sufficient emergency volume for all
waters  currently contained in the gypsum  pond by 1 April 2014. Talvivaara has,
in turn, noted to the ELY-Centre that the requested timetable is not technically
feasible and that a realistic deadline would rather be 15 May 2014.

The renewal of Talvivaara's environmental and water permit and the environmental
permit  application for uranium  extraction are being  processed at the AVI. The
Company expects decisions on both permits during the spring of 2014.

Following the corporate reorganization applications of Talvivaara Mining Company
Plc  and Talvivaara Sotkamo  Ltd, the Supreme  Administrative Court returned the
uranium  extraction permit  originally granted  in 2012 for  reassessment by the
Finnish  Government. Whilst the timetable for  the reassessment is currently not
known,  this has no impact on the processing of and decisions by AVI relating to
the environmental permit for uranium extraction.

Risk management and key risks

In  line  with  current  corporate  governance  guidelines  on  risk management,
Talvivaara carries out an on-going process endorsed by the Board of Directors to
identify  risks, measure their impact  against certain assumptions and implement
the necessary proactive steps to manage these risks.

During 2013, the Company's focus was on developing its hazardous risk management
and  contingency planning. As  a result, a  new risk register for environmental,
safety and accident risks was introduced. Contingency planning focused primarily
on hazard risks such power failure and dam or pond leakages.

Talvivaara's  operations  are  affected  by  various  risks common to the mining
industry,  such as  risks relating  to the  development of  Talvivaara's mineral
deposits,  estimates  of  reserves  and  resources,  infrastructure  risks,  and
volatility  of commodity prices. There are also risks related to counterparties,
currency  exchange ratios, management and control systems, historical losses and
uncertainties  about the future  profitability of Talvivaara,  dependence on key
personnel,   effect   of  laws,  governmental  regulations  and  related  costs,
environmental  hazards, and risks related to Talvivaara's mining concessions and
permits.

Liquidity and refinancing risks may arise as a result of the Company's inability
to  produce sufficient  volumes of  its saleable  products, particularly nickel,
unexpected  increase in production  costs, and sudden  or substantial changes in
the  prices of  commodities or  currency exchange  rates. In  the second half of
2013, the  liquidity and  refinancing risks  realized as  a result of persistent
production  problems relating to excess water, and  due to a substantial fall in
the  nickel  price.  As  a  result,  Talvivaara  and  its  operating  subsidiary
Talvivaara  Sotkamo Ltd.  were unable  to obtain  new financing  and applied for
corporate  reorganization, which for the  two companies commenced on 29 November
2013 and   17 December   2013, respectively.  Going  forward,  Talvivaara's  key
financial  and operational risks relate to the on-going corporate reorganisation
proceedings  and Talvivaara's ability to obtain sufficient additional funding to
continue its operations and to return to the planned ramp-up of production.

Operationally,  the Company has to date  demonstrated that all of its production
processes  work and  can be  operated on  industrial scale,  however the rate of
ramp-up  is  still  subject  to  risk  factors  including  the  reliability  and
sustainable capacity of production equipment, and eventual speed of leaching and
rates  of  metals  recovery  in  bioheapleaching.  In  addition,  the  return to
production  ramp-up remains subject to further  financing for the time being and
there  may  also  be  production  and  ramp-up  related risks that are currently
unknown or beyond the Company's control.

The  market price of nickel has historically  been volatile and in the Company's
view  this is likely to persist, driven  by shifts in the supply-demand balance,
macroeconomic  indicators  and  variations  in  currency exchange ratios. Nickel
sales  currently represent close to 90% of the Company's revenues and variations
in  the  nickel  price  therefore  have  a  direct  and  significant  effect  on
Talvivaara's  financial  result  and  economic  viability.  Talvivaara is, since
February   2010, unhedged   against   variations   in   metal  prices.  Full  or
substantially  full  exposure  to  nickel  prices  is  in line with Talvivaara's
strategy  and supported by the Company's view that it can operate the Talvivaara
mine,  once it  has been  fully ramped  up, profitably  also during  the lows of
commodity price cycles.

Talvivaara's  revenues are almost entirely in US dollars, whilst the majority of
the  Company's costs are  incurred in Euro.  Potential strengthening of the Euro
against  the US dollar could thus have a material adverse effect on the business
and financial condition of the Company. Talvivaara hedges its exposure to the US
dollar  on a case by case basis with  the aim of limiting the adverse effects of
US dollar weakness as considered justified from time to time.


Personnel

Talvivaara's  headcount decreased somewhat from the previous year and was 549 at
the  end of 2013 (2012: 588). At the  end of 2013, 87.1 per cent (2012: 88.1 per
cent) of Talvivaara's employees were men and 12.9 per cent (2012: 11.9 per cent)
were  women. The average age of  Company's employees was 37.9 years (2012: 37.8
years).

The  challenges of  2013 year were  also reflected  on the  Company's employees.
During  the year Talvivaara adjusted its headcount to the prevailing production,
first  in February and again in July by temporary lay-offs affecting part of the
personnel.  As the Company's financial condition continued to weaken, Talvivaara
applied  for corporate reorganization  in November and  started its third set of
co-operation  consultations for the year. These  were concluded in the beginning
of  January 2014 and as  a result, Talvivaara  decided to lay-off gradually 246
employees for undefined period to support the reorganization process.

The  salaries and  wages of  Talvivaara's personnel  are based  on industry-wide
collective  agreements. The total compensation consists of base salary and short
and  long term  incentive schemes.  Annual short  term incentive metrics include
personal   performance  and  company-wide  criteria.  The  Company's  long  term
incentive  schemes comprise Talvivaara's Stock Options 2007, Stock Options 2011
and  Group personnel fund to manage the  earnings bonuses paid by Talvivaara. In
addition,  the management holding  company Talvivaara Management  Oy is owned by
executive management and certain other key employees.

Corporate governance statement

Talvivaara issues its Corporate Governance Statement of 2013 and publishes it on
the Company's website at www.talvivaara.com on 27 March 2014, in connection with
the announcement of its full-year 2013 financial results.

Key events during the first quarter of 2014 to date

Participation in Fennovoima nuclear power project
Talvivaara announced on 21 February 2014 its support for the Fennovoima nuclear
power project, but noted that in the current circumstances the Company focuses
all its financial resources on the Sotkamo operation and the ongoing corporate
reorganization process. Therefore Talvivaara gives no commitment at the moment
for the additional funding of the Fennovoima project. Once further clarity into
the Talvivaara situation is obtained and the reorganization process proceeds,
the Company can reassess its ability to finance the Fennovoima project.

Changes in Talvivaara Management
Lassi Lammassaari, M.Sc. (Environmental Engineering) has been appointed Chief
Corporate Development Officer as of 27 February 2014. He will be leading a new
Corporate Development function, which will be focusing on industrial
engineering, planning and development. Lassi Lammassaari has held several
positions at Talvivaara since 2005, most lately as Senior Vice President -
Projects. He will be a member of the Executive Committee and will report to in
this new position to CEO Pekka Perä.

Short-term outlook

Market outlook
The LME nickel price has shown some recovery since the implementation of the
Indonesian NPI ore export ban in January 2014, moving from levels clearly below
USD 14,000/t to around USD 14,300/t recently. The still remaining NPI stocks in
China and the supply surplus that is anticipated to persist on the market during
the current year are likely to continue weighing on the nickel price in the
coming months such that substantial further price movements are not expected.
However, a cautiously more optimistic view towards the end of the year could be
taken, provided the Indonesian ore export ban stays in force and the nickel
price starts subsequently reflecting the increasing marginal cost of production
across the nickel industry and lack of new committed nickel projects to replace
depleting supply after the next few years.


Operational outlook
The operational outlook for Talvivaara is greatly dependent on the success to
closing, timing and extent of the short as well longer term financing solutions
currently under negotiation. With the Company's liquidity position allowing, the
key operational priority is to start reclaiming old primary heaps 2 and 3 as
soon as possible, preferably in the beginning of Q2 2014 at latest. Moving these
heaps to the secondary pad will allow the so far poorly leached ore to be
reconditioned and for leaching to be restarted. There is significant unleached
nickel in these two heaps, which will improve production in the coming months
prior to leaching from any newly mined and stacked ore can start contributing to
production. The Company plans to re-start mining in June, provided sufficient
financing is in place at the time. Operationally, Talvivaara believes the pre-
requisites for continued production ramp-up to be in place with substantial
improvements having been made over the recent months in bioheapleaching, as well
as in mining and materials handling prior to their suspension in November.
Furthermore, the metals plant is currently operating uneventfully.

Environmentally,  Talvivaara's key focus  is on managing  the overall site water
balance.  Firstly, this means continued reduction  of the overall catchment area
at  the site to minimise the amount  of precipitation and run-off waters needing
treatment  prior  to  release.  Secondly,  the  most  important water management
actions  also  include  maximising  the  operation  of the reverse osmosis water
purification  units and minimizing  the amount of  fresh water needed within the
operation  under  any  operating  conditions.  Thirdly,  the  Company targets at
managing  its process to be able to discharge all new precipitation entering the
site  as well as reducing  the volume of legacy  waters still contained on site,
thereby reducing the overall water balance of the mine area.


28 February 2014

Talvivaara Mining Company Plc
Board of Directors

[HUG#1765508]