2010-02-11 10:40:07 CET 2010-02-11 10:41:07 CET REGULATED INFORMATION Grigiskes AB - Notification on material eventGrigiskes AB launches construction of 17,5 MWh steam boilerCarrying out the project “The modernisation of the heat sector through the greater use of renewable energy resources” (No.VP3-3.4-ŪM-02-K-01-006) “Grigiskes”, AB and „Enerstena“, UAB signed a contract for design and equipment supply, on the 10th of February, 2010. Under this contract „Enerstena“, UAB undertook obligations to finish all designing and construction work of „Järnforsen Energi System AB“ sweedish company made wood fuel 17,5 MWh steam boiler on its own risks, forces, means and materials until the 31st of March, 2011. Value of the contract is LTL 17,6 mln. (EUR 5,1 mln.). The support of up to LTL 9,4 mln. (EUR 2,7 mln.) from the Cohesion Fund of the European Union and the budget of Lithuanian Republic for the implementation of the Project was granted. Gintautas Pangonis General Director (+370-5) 243 58 01 |
|||
|