2009-06-19 09:52:05 CEST 2009-06-19 09:53:05 CEST REGULATED INFORMATION Grigiskes AB - Notification on material eventHeat generation equipment modernize projectJSC Grigiskes has allotted a tender to receive a Cohesion fund grant for the heat generation equipment modernize project value of which is 19.1 million Litas. With the EU grant Company plans to obtain a 15 MW wood fuel steam boiler. It is supposed that the new steam boiler will produce 83 thousand MWh of heat energy per year. The objectives of the project are to provide energy more defensively and to reduce business risks. Following the recommendations of Ministry of Economy JSC Grigiskes received the approbation from National Control Commission for Prices and Energy for the project. Gintautas Pangonis General Director (+370-5) 243 58 01 |
|||
|