2009-04-24 08:42:04 CEST 2009-04-24 08:43:13 CEST REGULATED INFORMATION Lietuvos Elektrine AB - Notification on material eventSigned CCGT construction contract2009, 23 April AB Lietuvos elektrine and IBERDROLA Ingenieria y Construccion, S.A.U signed a contract for combined cycle gas turbine unit building, which cost 328 million EUR. A new block of 444 MW of power, the introduction to the operation date in 2012. General Director Pranas Noreika +370 528 33250 CFO Rolandas Jankauskas +370 528 33743 |
|||
|